It's now two weeks since the portico went up, and still we have no roof tiles! The SS said they would be done in the week that just passed, but all we saw was a water pipe pouring water into a pool in the ground (picture attached).
Given that each week costs us several hundred dollars, I am not happy with how slow things are going right now.
UPDATE: The SS just called and said he's been delayed by the following things
1. Corporate inductions (I think he's new to Metricon)
2. Rainy days
3. On the days that aren't rainy, he's been dealing with the fascia people. The fascia needs to be complete before roof tiles go on, but the fascia installers decided to re-order materials that were already at the site, and were waiting for those. So he says that is sorted out now and they just need to come in and do the fascia, then roof tiles can go on.